Billcost Version 2010.2 (August)- Release Notes
Billcost Version 2010.2 (August 2010) is now available.
The following database changes in Version 2010.2
- Fixed brickwork adjustment formula for garage doors to encompass the full spectrum of masonry selections
- Corrected error in selection for Stockpiled filling materials in Professional Database
- Make waterproofing a standalone trade again and move to after roofing
- Added selection options for S.A. Mortar in Professional Database
- Expanded the content of Paving formulae in basic database
- Changed foundation reinforcing formula in basic database to select Y10 stirrups @ 300mm intervals
- Copied drywall formula to Professional database
- Added Isoboard formula to Professional database
- Moved roof drainage options from Plumbing to concrete trades
- Added more options and priced to tools & equipment
Price increases:
- Aggregates and ready mix/precast products – 6%
- Plastics – 8%
- Wire – 15%
- Everite – 3%
- Copper Products – 6%
- Steel Window/Door Frames – 12%